Walking the line
The Brine Line Pipeline project starts at the Piccadilly mine and carries the brine water that is flooding the mine to the old mine in Cassidy Lake. There the Brine Water is processed to reduce the salt content to a similar level of seawater. Once finished, the processed water then travels through an existing pipeline that safely redirects it into the Bay of Fundy.

Zero down time
Safety Lead, Michael Brewer has been on site since January of this year. "There are 20 crews, about 140 people, on site and they've reached 137,815 work hours in six months. So far, there has been 1 first aid occurrence and no lost time incidents," says Brewer. The new 2-million-tonne potash mine and expanded milling operation in New Brunswick will be constructed over a four-year period at an estimated cost of CAN $1.66 billion.
"Maritime trades people are knowledgeable and great to work with. Safety is top priority and they're very receptive to the plans and training we've put into place."
- Michael Brewer, Leader In Safety

The Right of Way goes around properties, up and down mountains, under roads, through golf courses and past houses. The terrain is constantly changing and each type presents its own set of safety challenges.

"The project is complex with many areas of planning to consider with environmental protection and preservation, natural resources, residential properties, traffic control and above all, the safety of every person involved."
- Nils Myhren, Leader In Safety

What's new
We couldn't wait until the fall issue of "News Leader" to share the exciting details of Leader In Safety' latest project. We're working with Robert B. Somerville Co. Ltd. on the Brine Line Pipeline installation for Potash Corporation of Saskatchewan's Picadilly Potash Mine in Sussex, New Brunswick.

Drill bits
Out of the 32km pipeline, 12 kms will be horizontally drilled making it one of the largest drill sites in Canada. There are six drills on site drilling through rock, sand, clay and gravel.

Confined space rescue
Leader In Safety' Confined Space Rescue Team is available to evaluate your job site, identify confined spaces, assess air quality and indicate potential hazards. Unsafe conditions will be eliminated or controlled, entry permit systems will be implemented and site-specific emergency rescue plans formulated.

>> Contact us with your questions, concerns or for more information at www.leaderinsafety.ca

Any project, any size, anywhere in the world, Leader In Safety is there to minimize risks, make it safe for employees and protect your company's bottom line.

>> Call today for a safer tomorrow: 1-866-939-7999

Special thanks to the Telegraph-Journal and Potash Corporation of Saskatchewan Inc., for their assistance with the information in this newsletter.


NEWSLETTERS


Newsletter Home 2012 Winter 2012 Spring 2011 Holiday 2011 Summer

Download Adobe Reader


Leader In Safety
62 Knupp Road
Barrie, ON L4N 0R7
Tel. 705.791.4281
Fax. 705.722.9094
Click here to find job opportunities with Leader In Safety